Manually Map a Risk to Multiple Activities
Manually map a risk to multiple activities.
To manually map a risk to multiple activities, complete the following steps:
- Select the S3 // Risk tab.
-
On the Views group, click:
-
- In the Risk Register (left pane), select the risk that you want to map.
- In the Activities panel (right pane) Mapped column, select the check box next to the activities that you want to map to the selected risk. After mapping has been applied, you have the option to override mapped activities using the Mappings tab beneath the Risks (left pane).
- (Optional) In the Risk Register (left pane) Absolute Mapping column, select the check box next to the risk(s) for which you want to use absolute mapping. Absolute mapping is applied to all activities that are mapped to that risk.